28 October 2007:
The Merdeka Walk project has come to an end. We were very grateful that the project has completed before the dateline. Thanks to Maxis Bridging Communities and the administration of the school for sponsoring the project. Thanks to our treasurer, Puan Noridiamiyanti for her time and effort to update the budget details.

No

Date

Item

RM

1

9/9/07

Stationery (Rainbow Art)

398.80

2

9/9/07

Merdeka Walk & Maxis Cyberlinq labels

20.00

3

10/9/07

Stationery (Kiang Trading)

39.40

4

1/10/07

Blue cloth (KT Textile)

67.50

5

6/10/07

Printing & Laminating (Jasamax)

180.60

6

8/10/07

Red ribbons (Butik Nona)

35.00

7

9/10/07

Red and White ribbons(Unik Handiwork)

66.00

8

11/10/07

Printing & Laminating (Jasamax)

52.00

9

16/10/07

Metal wire (Ken Hoe Trading)

6.80

10

19/10/07

Stationery (Kiang Trading)

40.50

11

20/10/07

Stationery (Kiang Trading)

10.25

12

24/10/07

Banner (Khazanah Alam)

140.00

13

24/10/07

Stationery (Kiang Trading)

23.85

14

24/10/07

Administration

50.00

Grand total

1130.70